Friday, July 31, 2009

Parking Lot Light & Library Shelves



.

Tuesday, July 28, 2009

Parking Lot Work Begins

Parking lot work and some more tiling in hallway and Music Room.

Saturday, July 25, 2009

Server Room

Server room wiring. You see some of the about 8 miles of cable for the network in all of the buildings.
Computer rooms set up with the new LCD panel monitors.
Tiling going ahead in phase 2.

Wednesday, July 22, 2009

Tiling of Hallway

Trees cut in preparation for the parking lot to get finished on the site of the now landfilled Northwest Hall.

Tiling of the halls and music room has begun. They have started at the Administrative end and are working down through the entire hallway. They are catching the music room on the way. One pic shows preparation in the music room for the tiling today.

Grass loks great and has been mowed for the first time. Needs another right soon.



.

Wednesday, July 15, 2009

Northwest Hall Slab Demolition

The turkey shed, chicken house, storage room, art room, or whatever it was used for when you were here was the last part of the structure of NW to go down. Many bats were sheltered there.
Next comes the slab and there was no way they expected to find so much concrete under this building. Much digging along side some of the footings was needed to get them out even with old T-Rex on the job.
There is still work left to do to get it all cleared.



.

Video: Ingram Update,Outside Academic Center, Northwest Concrete



.

Saturday, July 11, 2009

Video: Northwest Demolition

First Part of the Northwest Demolition:
http://www.ilcpublicity.org/video/nwdemopart1.wmv

Second Part of the Northwest Demolition:
http://www.ilcpublicity.org/video/nwdemopart2.wmv

Northwest Demolition Cleanup:
http://www.ilcpublicity.org/video/nwcleanupsite.wmv

Friday, July 10, 2009

Northwest Hall Demolition

You see some of the before, during, and after a days work on the deeeestruction of the old barn known as the NW Hall.



.

Thursday, July 9, 2009

Northwest Hall & Administration Offices

Northwest going little by little as the crowns come off.



.

Saturday, July 4, 2009

Video: Inside Tour



.

Friday, July 3, 2009

Video: Sodding



.

Thursday, July 2, 2009

Sod

The move is mostly completed and things are quite disarrayed.
All ages of workers showed up today. (Pfeiffer grandchild)
Had a walk-through today with the designer and builders.
Window washers hard at it also.
Sod, sod, and more sod. Good help and a big job done.



.

Wednesday, July 1, 2009

Video: Landscaping



.

Moving & Lawn Prep

Moving is going on daily.
The president has found a place to work from and dream from.
Mrs. Pfeiffer has a cozy little nook to try and get some work done.
The Sydows are moving the rocks around the buildings; leveling, fertilizing, and seeding large areas to the North, East, and West of the building. You see some before and after pics.



.