Many of the pictures are courtesy of Cheryl Meyer and retired Prof. Ron Roehl. You may also click on the slide show in order to access directly the Picasa album for additional features (e.g., seeing the pictures larger, ordering pictures for printing, etc.).

You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!

Saturday, April 11, 2009

Flagpole Area Prep

Pics and report courtesy of Prof. Ron Roehl

Not much update but a few pics to show some progress.

The trench is for the circular wall and flagpole area. Needs a good foundation.

Roofers made a little headway.

Lots of wood in the rafters.

Some perspective pics.



.

Friday, April 10, 2009

Video: Bulldozing & Roof Sheeting



.

All Rafters Up

Pics and report by Prof. Ron Roehl

Just a few to catch you up on some of the progress.
All the rafters are up now.
The roof is on all of the building.
The roofers are on site and getting the shingling started.
The downspouts are being connected to the storm drains.
The area is being prepared for the slab in the library and computer rooms.
Also the base for the flag pole area is being readied.



.

Thursday, April 9, 2009

Video: Storm Sewer Lines



.

Video: Peaks of Administrative Section



.

Wednesday, April 8, 2009

Peaks on Administration Area

Just two pics to show the progress.

One is the side view of the office area. It is the far north section of phase 2.

The other is taken from the west side to show the two peak sections and the entry area to the business and administration area.

The slab will be poured hopefully early next week.

The crane will be packed up and out of here by tonight.



.

Monday, April 6, 2009

Video: Trusses & Roof Sheeting



.

Rafters Over Administration Area

Pics and report by Prof. Ron Roehl:

Trusses are going up on the last section. We will finally run out of trusses and that's good. Windy today so it was a little tougher setting the rafters.



.

Friday, April 3, 2009

Video: More Walls of Adminstrative Center



.

Closing in the Roof

Pics from Prof. Ron Roehl:

Working on walls for the interior and trying to close in the roof.
Weather is cool but good working weather.



.

Wednesday, April 1, 2009

Video: Walls of Administrative Section



.

Walls for the Administrative Offices

Progress on the walls of the office section of phase 2:



.