Pics and report courtesy of Prof. Ron Roehl
Not much update but a few pics to show some progress.
The trench is for the circular wall and flagpole area. Needs a good foundation.
Roofers made a little headway.
Lots of wood in the rafters.
Some perspective pics.
.
Many of the pictures are courtesy of Cheryl Meyer and retired Prof. Ron Roehl. You may also click on the slide show in order to access directly the Picasa album for additional features (e.g., seeing the pictures larger, ordering pictures for printing, etc.).You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!
Saturday, April 11, 2009
Friday, April 10, 2009
All Rafters Up
Pics and report by Prof. Ron Roehl
Just a few to catch you up on some of the progress.
All the rafters are up now.
The roof is on all of the building.
The roofers are on site and getting the shingling started.
The downspouts are being connected to the storm drains.
The area is being prepared for the slab in the library and computer rooms.
Also the base for the flag pole area is being readied.
.
Just a few to catch you up on some of the progress.
All the rafters are up now.
The roof is on all of the building.
The roofers are on site and getting the shingling started.
The downspouts are being connected to the storm drains.
The area is being prepared for the slab in the library and computer rooms.
Also the base for the flag pole area is being readied.
.
Labels:
pics
Thursday, April 9, 2009
Wednesday, April 8, 2009
Peaks on Administration Area
Just two pics to show the progress.
One is the side view of the office area. It is the far north section of phase 2.
The other is taken from the west side to show the two peak sections and the entry area to the business and administration area.
The slab will be poured hopefully early next week.
The crane will be packed up and out of here by tonight.
.
One is the side view of the office area. It is the far north section of phase 2.
The other is taken from the west side to show the two peak sections and the entry area to the business and administration area.
The slab will be poured hopefully early next week.
The crane will be packed up and out of here by tonight.
.
Labels:
pics
Monday, April 6, 2009
Rafters Over Administration Area
Pics and report by Prof. Ron Roehl:
Trusses are going up on the last section. We will finally run out of trusses and that's good. Windy today so it was a little tougher setting the rafters.
.
Trusses are going up on the last section. We will finally run out of trusses and that's good. Windy today so it was a little tougher setting the rafters.
.
Labels:
pics
Friday, April 3, 2009
Closing in the Roof
Pics from Prof. Ron Roehl:
Working on walls for the interior and trying to close in the roof.
Weather is cool but good working weather.
.
Working on walls for the interior and trying to close in the roof.
Weather is cool but good working weather.
.
Labels:
pics
Wednesday, April 1, 2009
Walls for the Administrative Offices
Progress on the walls of the office section of phase 2:
.
.
Labels:
pics