Photos courtesy of Prof. Ron Roehl who reports:
No outside pics today. They are just working on the trim outdoors trying to finish so they can start the siding.
Taping is complete inside and they are beginning to cover the windows so they can sand, do another coat, texture and paint. They are moving.
The hallway up above is a mass of pipes, large and small as you can see.
The mechanical room is shaping up as they have installed the pumps and added the pipes to the building. Next will be the connections to the wells which are just across the room. This is quite a system.
The blue wires are data wires going down the hallways and appearing in the classrooms. This is all local work. The mass of wires in the server room are the ends of the data cables that will be hooked to the server. Big job done by Dean Marzofka, Prof. Ross Roehl, and Nick Marzofka. There are about 40 drops needed to supply all the classrooms. You can see some of the blue cables where they appear in the classrooms.
.
Many of the pictures are courtesy of Cheryl Meyer and retired Prof. Ron Roehl. You may also click on the slide show in order to access directly the Picasa album for additional features (e.g., seeing the pictures larger, ordering pictures for printing, etc.).
You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!