You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!
Monday, March 30, 2009
Peaks on Main Part of Phase 2
Pics and report by Prof. Ron Roehl:
They put the peaks on today on the largest part of phase 2.
The perspective pics you will see show how large this section really is. There are a lot of different purpose rooms in this section including the library.
.
They put the peaks on today on the largest part of phase 2.
The perspective pics you will see show how large this section really is. There are a lot of different purpose rooms in this section including the library.
.
Labels:
pics
Saturday, March 28, 2009
Rafters for Phase 2
Pics submitted by Prof. Ron Roehl and Cheryl Meyer:
Report by Prof. Ron Roehl:
Some pics from early in the week.
Outside scenes to show the week's progress and the unfinished rafters on this section. They each need a peak yet also.
Inside pics will give an idea of the size of the area.
Door frames waiting to be put in.
Practice room shots inside the music/shelter room.
.
Report by Prof. Ron Roehl:
Some pics from early in the week.
Outside scenes to show the week's progress and the unfinished rafters on this section. They each need a peak yet also.
Inside pics will give an idea of the size of the area.
Door frames waiting to be put in.
Practice room shots inside the music/shelter room.
.
Labels:
pics
Thursday, March 19, 2009
Rafters Ready
Pics and report by Prof. Ron Roehl:
Worked mostly on the ground today getting rafters etc. ready to go up. Tomorrow should see some go up.
Grouting for the tile is finished in the Science rooms and looks real nice.
.
Worked mostly on the ground today getting rafters etc. ready to go up. Tomorrow should see some go up.
Grouting for the tile is finished in the Science rooms and looks real nice.
.
Labels:
pics
Wednesday, March 18, 2009
Walls Continue for Phase Two
Pics and report courtesy of Prof. Ron Roehl:
Tiling is about finished in the Physics/Chem room and the Biology room. It will take approximately a day to grout the rooms
A couple pics are from early this morn and of course some later.
The next area that will have a peak has been walled in as you can see.
A couple of perspective pics might help some of you.
.
Tiling is about finished in the Physics/Chem room and the Biology room. It will take approximately a day to grout the rooms
A couple pics are from early this morn and of course some later.
The next area that will have a peak has been walled in as you can see.
A couple of perspective pics might help some of you.
.
Labels:
pics
Tuesday, March 17, 2009
Walls Start Going Up for Phase Two
Pictures and report provided by Prof. Ron Roehl:
The boys are playing with their sticks today and when they finish it looks like a wall of phase 2.
Walls, then rafters and slab will come after that.
The tile looks great ...
One perspective shot from the path toward North Hall.
.
The boys are playing with their sticks today and when they finish it looks like a wall of phase 2.
Walls, then rafters and slab will come after that.
The tile looks great ...
One perspective shot from the path toward North Hall.
.
Labels:
pics
Monday, March 16, 2009
Footings and Tiling
Pics and report by Prof. Ron Roehl:
Deep footings ready for the walls on top with safety tips on top.
Forms in place and about ready for the pour.
Pouring done and finishing being done. It goes up from here.
Lab floors are getting the tiling done. They look great.
.
Deep footings ready for the walls on top with safety tips on top.
Forms in place and about ready for the pour.
Pouring done and finishing being done. It goes up from here.
Lab floors are getting the tiling done. They look great.
.