- All bids are now in and have been awarded.
- Original estimate was $2.4 M plus architect's fees, which we originally estimated at $100-150 K.
- We have added the geothermal system, masonry storm shelter room, and somenecessary campus infrastructure items (primarily storm water management andretention pond)
- Final GMP has been set at $2.67M, although we anticipate that number will golower as construction proceeds
- A low interest construction loan is being secured from Wells Fargo Bank atapproximately 5.25% This line of credit may or may not be utilized.
- Revised estimates call for Phase One to be completed Jan-Feb of 2009 and full project completion May-June of 2009
Many of the pictures are courtesy of Cheryl Meyer and retired Prof. Ron Roehl. You may also click on the slide show in order to access directly the Picasa album for additional features (e.g., seeing the pictures larger, ordering pictures for printing, etc.).
You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!
Sunday, October 5, 2008
Update from Building Committee
ILC Building Committee Chairman, Pastor Michael Roehl reports: