Last of the roof sections being shingled. Other side is finished.
Front walk concrete pad and part of concrete walkway
All outside walls insulated and some sheetrock up on the ceilings
Forms are mostly in for the circular concrete work to done in front of the Admin entrance. The flagpole with lights and the college name with lights will be part of this feature. It looks like one big slab but there will be cuts made in it to dress it up.
Hangers for the drop ceiling in the music room are being put in place.
.
Many of the pictures are courtesy of Cheryl Meyer and retired Prof. Ron Roehl. You may also click on the slide show in order to access directly the Picasa album for additional features (e.g., seeing the pictures larger, ordering pictures for printing, etc.).
You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!