- Completion date for Phase 1 is February 13, 2009
- Phase 1 to be sheeted (roof and walls) by December 12
- Shingle crew to complete work the week of Dec. 15
- All 50 geothermal system wells have been dug
- Building dried-in and temp-heated prior to Christmas
- Trim changed to oak in many areas of Phase 2 due to donation of materials from CLC member in Markesan area
- Stained glass representations of Luther’s Seal and ILC Logo for gable ends of west elevation are being constructed off-site. Cost of materials only not to exceed $5K. M&J will construct gable framing and lighting at no additional cost.
- Tentative completion date for Phase 2 is May 1

You may scroll down to the bottom of this blog page to see two different views of the live web cams focused on the building site!
Sunday, December 7, 2008
Update from Building Committee
There was a progress meeting with Market and Johnson this past Friday (Dec. 5) regarding the building. Here are some notes: